If you haven’t, read the introduction here!
The following is adapted from the briefing we read together at the beginning of the session and includes the resulting Value Stream Map
Workshop Structure
Objective of Session 1
To Collaboratively map out the entire deployment process on a flow chart. The goal is not to collect every step, but to get the main picture, so we can visualize the current state of the workflow. We’ll be mapping the latest deployment done to date. It’s important to focus on a specific deployment because we have actual data on how it happened, which will help us with the mapping, impact, and cost analysis.
Session Structure
The goal was to provide the supporting data to help in the discussion and mapping exercise. Relevant metrics that help us analyze the deployment are:
Because value is only delivered when our code is running in production, we must ensure that not only we are delivering fast flow, but that our deployments can also be performed without causing chaos and disruptions.
Frequent, smaller deployments reduce the complexity of each release, lowering the risk of major failures. Quick detection and correction of problems, facilitated by robust feedback and telemetry systems, prevent issues from escalating. This maintains system stability and reliability.
How Feedback and Telemetry Help: Implementing continuous feedback and telemetry allows for real-time monitoring of deployments. It enables the team to quickly identify anomalies or issues as they arise, leading to immediate corrective actions. This continuous feedback loop and adjustment is key to maintaining high-quality, reliable services.
Streamlining and automating deployment processes cut down on lead times, improving overall efficiency and reducing manual effort.
Focus on minimizing time-consuming and repetitive manual tasks. This shift allows us to better utilize our skills and expertise in engineering to better support our customers and colleagues. By optimizing our processes, we can significantly boost efficiency without increasing resource allocation. We need to make sure that we’re doing the things that provide the most value, or we’ll get drowned in inefficiencies and take too long to get things done.
Shorter lead times enable quicker feedback from users, feeding a cycle of continuous improvement and learning.
This is essential to keeping up with the compound interest cost of technical debt, while maintaining both the service reliability and the ability to develop new features.
Longer lead times often mean larger, more complex deployments, increasing the likelihood of errors and the time required to resolve them. This can lead to situations where customers notice issues before we do, damaging trust and reputation.
Delays in deploying new features or fixes can lead to customer dissatisfaction, as customers take longer to get value from the deployed features.
Slow deployment processes can result in missed market opportunities and an inability to respond promptly to competitive challenges.
By reducing time spent on manual, process-heavy tasks, we can redirect our efforts towards activities that directly benefit customers, support other teams, and contribute to the company’s overall goals.
Our Lead Time: As mentioned, our current total lead time for the deployment is 21 days. During this workshop, we explored strategies to reduce this time frame, making our deployment process more agile and efficient.
We can measure Deployment Lead Time and Percent Complete and Accurate (%C/A) for each deployment, regularly reviewing these metrics to see the effectiveness of our actions and make necessary adjustments.
We’re looking at the process that transforms ideas into value generated for the customer. It’s important to look at how much this is costing us now, and as we make improvements, observe what is happening to the costs.
This will also help motivate people towards making improvements in the process: money talks.
I made an initial cost estimate for this particular deployment, which will be useful as we improve our deployments to see what happens to our costs. This helps us understand the impact of our work.
I can’t share the cost estimation but I can share some components that can be used to estimate costs for deployments
How do you estimate the costs and revenue from features/deployments? I’d love to hear your feedback.
During the session, we mapped the process from the creation of a User Story detailing the feature, to when it is deployed to the customer.
We included defects and rework in this map and color-coated parts of the work as Manual, Automated, Errors/Defects.
Now we have mapped our value stream. We’re in a position to start identifying areas of waste, so we know exactly what we need to improve and what’s the impact. We did that in session 2.
In the next article, I’ll go over what we did in session 2 and what results we achieved. Here’s what’s coming up:
As we wrap this up, I’m excited to hear from you! Please add your feedback or questions here, I’ll get back to you.
Thank you for reading, have a great day!